At civil engineering construction sites, we often hear comments such as , “Even though we go to the trouble of taking 3D measurements, the final deliverables are still traditional drawings,” or “3D data is treated merely as reference material, and maintaining two separate sets of data is the norm.”
While there is a growing call for on-site efficiency and digital transformation (DX), we would like to introduce a case study of the Ehime Prefecture Department of Public Works’ efforts to address the challenge that “measurements have become easier, but the workload hasn’t decreased.”
In October 2025, the Ehime Prefecture Department of Public Works revised and published the “Guidelines for the Implementation of Construction Projects Utilizing ICT (Latest Edition).”
These guidelines establish the use of 3D data—from initial surveying to construction management and the final delivery of deliverables—as a “standard business process” for public works projects. They clearly state that 3D data (including point cloud data acquired via 3D scanners, LiDAR sensors, etc.) can be utilized and electronically submitted as official deliverables.
With the official announcement of a shift away from the traditional drawing-centric approach—without requiring dual management—a future is now in sight where the convenience of 3D scan data—previously viewed as “useful but difficult to use for delivery” or “ultimately requiring dual management alongside conventional methods”—will directly lead to labor savings on construction sites.
↓↓↓ Click here for the full text of the Ehime Prefecture ICT Guidelines ↓↓↓
https://www.pref.ehime.jp/page/8140.html
For construction projects utilizing ICT in Ehime Prefecture, the following process is generally followed for ICT-based construction.
Among these,Scanat can be utilized in processes such as “3D pre-construction surveying,” “3D as-built management,” and “3D data delivery,”expanding the possibilities for completing the entire process from as-built management and inspection to final delivery.
Point cloud data and 3D models acquired using these devices are also eligible for electronic delivery as construction as-built documentation, provided certain conditions are met.
① Suited for the Era of Area-Based Management
The new ICT guidelines have established “area-based as-built management”—which ensures sufficient point density—and pass/fail determination using heat maps as standard approaches, moving away from the traditional “cross-section and point” management methods.
Scanat Since [Company Name] specializes in 3D scanning that captures the entire job site as a surface, it is highly compatible with this management approach.
Numerous benefits can be expected, including reduced effort in creating management documents, streamlined inspection processes, and improved explanatory power through job site visualization .
② 3D Technology Officially Permitted Even for Small-Scale Construction and Repair Projects
Under these guidelines, the use of ICT equipment for surveying has been expanded to include small-scale construction projects.
Even without using expensive laser scanners or UAVs, as-built management using mobile devices or ground-based photogrammetry is now officially recognized for work categories such as ICT earthwork (less than 1,000 m³) and ICT paving (repair work).
This lowers the barrier posed by the notion that “3D measurement is impossible without expensive equipment,”Scanatmaking it possible to utilize even simple 3D scanning technologies like this
with an eye toward final delivery.③ Cases where 3D data creation is “recognized as an expense”
For ICT-based construction projects initiated at the contractor’s request, it is also explicitly stated that costs associated with “3D as-built surveys” and “3D design data creation (including revisions)” can be accounted for as design changes.
As a result,
・3D data creation does not become “out-of-pocket work”
・Scanat the barriers to adoption and utilization are lowered
.
As described above,Scanat 3D data captured in this manner is becoming a practical option for ICT-driven construction projects, offering the following benefits:
・An alternative to expensive specialized equipment
・Suitable even for small-scale construction and repair projects
・Avoids duplicate management
・Technology that supports everything from as-built management to electronic delivery
.
Rather than simply “measuring and calling it a day,” it provides “3D data that can be used all the way through to delivery”Scanat .
As a powerful ally in helping construction companies meet future demands for operational efficiency through mobile LiDAR, our clients have expressed high expectations, stating, “If adopted as a proposal-based ICT construction project, we can expect bonus points in construction performance evaluations, which will lead to a higher probability of winning future contracts.”
The case study from the Ehime Prefecture Department of Public Works reflects the policy direction of the Ministry of Land, Infrastructure, Transport and Tourism, and we anticipate that it will spread nationwide in the future.
We will support companies that wish to be among the first to adopt this model as a best practice, accumulate know-how, and gain a competitive edge.